Zone Starter Toe Sleeve Successful Openings 11-Months After Install

Challenge

A large operator in the Marcellus/Utica had drilled multiple DUC’s with WellBoss Zone Starter Cycling Toe Sleeves, which were uncompleted for 11+ months. When going in to open these tools the operator was looking for the following:

  • Perform casing integrity test at 9,500 psi for 30 mins.
  • Fully open after cycling pressure and achieve
    formation breakdown
  • Initiate formation injection

Solution

Zone Starters are designed with reliability in mind! Wellbore conditions such as: temperature, casing fluids gasses and cement are variables that can impede the functioning of a toe sleeve. By incorporating coatings to moving parts, specialized greases, reliable/redundant sealing mechanisms and fit for purpose metal selections, operators can have confidence in opening Zone Starters
reliably.

Results

Installation Date: July 17, 2019
Opening Date: May 3, 2020

  • 09:52 hrs: Start Stage 1 Toe pop – PT Csg to 9,900 psi for 30 min good test, 1st Cycle
  • 10:28 hrs: Bleed to 0 psi – 5 min
  • 10:51 2nd cycle Pressure to 9,900– 5 min
  • 10:57 hrs: Bleed to 0 psi – 5 min
  • 11:11 hrs: Toe opened @ 5,059 psi. Injected 40 bbls @ 8 bpm x 6,400 psi.